Client

Bam Nuttall

Project

Redhill Station

Sector

Transport - Rail

Location

Redhill

Year

2017

Duration

28 Weeks

The Brief

KH Engineering Services were awarded the contract by Bam Nuttall to install all Mechanical and Electrical services to the newly constructed Platform 0.
The installation & commissioning of new services were to be installed while maintaining the existing services for the station.

The scope of works consisted of the following:
• Relocate / remove existing equipment located at the subway entrance to Platform 0
• Provide new DNO service to station and associated distribution
• Main Switchgear
• Sub main cables and distribution boards
• Final circuit wiring
• Lighting and emergency lighting installation
• Small power installation
• Containment
• Earthing and bonding
• Installation of Help Point
• Installation of Fire Alarm System
• Installation of interface between fire alarm, emergency lighting, and secondary means of escape
• Installation of CCTV
• Installation of mechanical services (water) to pre constructed toilet block
• Inspection, testing & commissioning

The Approach

KH Engineering Services worked in conjunction with Bam Nuttall to coordinate the initial site investigations, and the removal / relocation of services within the subway adjacent the proposed entrance to Platform 0.

A programme of both normal working hours and engineering working hours were agreed as part of the contract, with a final key date of operation set for the 2nd of January 2018 was approved between all parties.

Swipe to view photos
The Challenges

During the course of the contract it become apparent the existing DNO service to the station was insufficient for the additional supply. This information was passed to the client and preliminary designs were completed however, due to late client approval, only 3 months were given to supply a new 400Amp service for the station.

To meet this key requirement an additional labour team was drafted into the project and the programme altered to reflect the changes with the need to meet the key date unchanged.

In addition to the extra works, further programme changes had to be completed due to the late completion by 3rd party contractors on key building structures within Platform 0.
This included the canopy structure, waiting room, and toilet block all failing to meet the key dates.

Due to the above, KH Engineering Services made further amendments to the programme and devised a solution of an additional team working night shifts in order to regain the lost time.

The Delivery

KH Engineering Services were the responsible contractors for this project and construction responsibility. We were able to complete the project in line with the completion date with no RIDDORS, and extensive improvement opportunities presented to the client.

KHES were delighted to report zero defects at practical completion with the final account pre-agreed.

The Outcome

KH Engineering Services managed the interface between UKPN and other contractors to supply a fully functional DNO services within a limited time, allowing the project to meet all required key dates.