Client

Abellio Greater Anglia

Project

Southend Victoria Hand Bash

Sector

Transport - Rail

Location

London

Year

2017

Duration

5 months

The Brief

KH Engineering Services were the Principal Contractor for the Southend Victoria Hand Bash project.

A new train hand bash facility at Southend Victoria depot was required to accommodate 8 car trains as part of the use of a new wash plant.
Due to the condition of existing track and sleepers, improvement works were required prior to the installation of the new facility.

The Approach

Within this design strategy, apron slabs were formed to run the full length of the train. GRP grating covers were installed providing a level working platform at rail level where the discharge has been directed into the new draining system that ran the length of the wash road down to the interceptor.

KH Engineering Services identified that the existing power supply was inadequate to serve the additional services required for the new facility therefore KHES installed a new DNO supply within the feeder pillar (FP3) located in the south-east corner of the BTP car park.

Summary of works:
• Removal of the existing track and sleepers.
• Pre-dig to accommodate the new bases for the new track.
• To form 9no. 20m long heavily reinforced concrete bays with their own independent drainage that links to the existing catch pits. This will make a total of 180m of concrete bases for the new track to be installed to accommodate an 8-car train.
• To provide and install 8 watering points, 4no each side. All pipework having trace heating installed as well as the appropriate lagging. These were fed from an independent pump that is situated behind the buffer stops.
• To provide 150 lights, 75no each side. All lighting and associated power was fed from the new DNO installed in the BTP carpark at the back of the station mess hut.
• To install a new rail track.

The new Hand Bash facility required the following Mechanical & Electrical works:

• New DNO supply
• Main switchgear
• Submain cabling and distribution boards
• Containment
• Final circuit wiring
• Lighting and emergency lighting installation
• Small power installation
• Earthing and bonding
• New Earth rod/electrode installation
• New traction bonding link to main earth bar
• Inspection, testing & commissioning
• Feeder pillars including concrete base

Swipe to view photos
The Challenges

Issues and delays to the project:
• Asbestos was identified.
• Working within 2.75m of OHLE.
• Ensuring lighting level adequacy for all stakeholders.
• Late design change for structural slabs to incorporate new client canopy design.
• Unexpected existing services discovered.
• Extensive Value Engineering opportunities proposed.

The Delivery

KH Engineering Services were the Principal Contractor under CDM for this project and carried both the design and construction responsibility.

Structural design changes influenced the lighting design; these late changes affected progress however, KHES were able to complete the project in line with the completion date with no RIDDORS and extensive improvement opportunities presented to the client.

KH Engineering Services were delighted to report zero defects at practical completion with the final account pre- agreed.

The Outcome

KH Engineering Services were delighted to report zero defects at practical completion with the final account pre-agreed.

Related case studies...